Metrodome
To make way for the new US Bank Stadium in downtown Minneapolis. Frattalone was hired to complete demolition of the iconic 900,000 SF, 63,000 seat Metrodome stadium. The precast and cast-in-place concrete structure was demolished using a combination of controlled explosives and mechanical demolition. Frattalone acquired a high reach demolition excavator for the project. Over 5,000 tons of scrap metal and 80,000 tons of concrete were recycled during the process. Work was completed one month ahead of the four-month schedule, during one of the coldest winters in Minnesota history.